Specifies the estimate at completion (EAC) total price for a job task line. If the Apply Usage Link check box on the job is selected, then the EAC (Total Price) field is calculated as follows:

Usage (Total Price) + Remaining (Total Price)

You can use the value in this field to track performance and the projected total cost of the project.