Open the Adjust Resource Costs/Prices window.

Adjusts one or more fields on the resource card. For example, you can change the direct unit cost by 10 percent on all resources from a specific resource group. The changes are processed immediately after the batch job is started. The fields on the resource card that are dependent on the adjusted field are also changed.

To select the field to be adjusted, choose one of the Adjust Field options on the Options FastTab.

Important
This batch job does not create or adjust alternative costs or prices for resources. It only changes the relevant fields on the resource card.

The adjustment takes direct effect on the resource table, so check your settings thoroughly before you choose the OK button.

Options

Field Description

Adjust Field

Select the option for the field that is adjusted by the batch job. You can select only one field at a time.

Adjustment Factor

Enter the factor that the prices are multiplied by. For example, if the direct unit cost of a resource is LCY 100 with an Adjustment Factor of 1.1, the batch job increases the new direct unit cost to LCY 110.

Rounding Method

Enter a code for the Rounding Method that is used to determine the new prices. To see the existing rounding method codes, choose the field.

Tip

See Also